On May 18, the first 17 households in the land clearance area of Long Thanh International Airport project (Dong Nai province) received about 70 billion VND in compensation. It is expected that 1,810ha of priority land for phase 1 of the project will be handed over in 2020.
Urgent clearance
The project of Long Thanh international airport (Long Thanh airport) is one of the key national projects. Prime Minister Nguyen Xuan Phuc has instructed Dong Nai province to consider this a political task of the province, focusing on the project of land acquisition, compensation, support and resettlement at Long Thanh airport.
The Prime Minister assigned the task of completing the disbursement of the allocated capital (17,057 billion VND) in 2020 as committed, so that Long Thanh airport can start construction in the first quarter of 2021, complete phase 1 in year 2025 according to the Resolution of the National Assembly.
Up to now, the total area of site clearance for phase 1 of Long Thanh airport is 1,810ha out of the total of more than 5,000ha of the project. Of these, there are 630ha of 1,007 households and individuals. 600 of these households have been identified with different levels of compensation. The rest of the area belongs to Dong Nai Rubber Corporation One-member LLC.
Currently, the authorities have identified the remaining 407 households to buy and sell land with handwritten paper and need to verify the land area, the People's Committee of Long Thanh district is making efforts to early approve the compensation plan and pay compensation. , support.
“For records of land plots without owners, the locality will comply with the regulations that are to transfer compensation and assistance money to accounts at the State Treasury. The next two compensation rounds will be held before June 1-6 and before June 15, ”said Mr. Le Van Tiep, Vice Chairman of People's Committee of Long Thanh district, Dong Nai province.
In addition to the 1,810ha of first clearance clearance, the authorities have identified more than 2,400ha of land under the management of more than 4,300 households and individuals. The locality has made an inventory of more than 480ha of land for 654 households and individuals.
In the coming time, the People's Committee of Long Thanh district will continue to carry out the inventory work for an area of nearly 1,900 ha of the remaining 3,700 households. Dong Nai province has committed to the Government, in the second quarter of 2021, will hand over the entire project site to the investor.
In order for households subject to early clearance to have a place to resettle, stabilize their lives, create good public opinion for the next site clearance, at the end of April 2020, Dong Nai People's Committee has started construction of the area. Loc An - Binh Son resettlement, more than 280ha wide.
The resettlement area will welcome the first 700 households in the area of clearance to build Long Thanh airport. It is expected that by August 2020, Dong Nai province will hand over land to the first households.
Just land acquisition, just complete the resettlement area
During the meeting on May 15 between the People's Committee of Dong Nai province and the delegation of the National Assembly of Dong Nai province, opinions are still raised. The first is that the infrastructure system of the resettlement area has not been completed yet. Secondly, up to now, Dong Nai People's Committee has disbursed 10% of the total capital of more than 17,000 billion VND that the Government has arranged for the province to disburse in 2020.
Regarding the resettlement area infrastructure, Mr. Nguyen Anh Tuan, Deputy Director of Dong Nai Construction Investment Project Management Board, said that he has started and implemented the construction of 5 priority bidding packages, which are 5 transportation routes. main site at Loc An resettlement area - Binh Son, to be completed in October 2020.
It is expected that in August 2020, the Management Board will complete infrastructure for 1,000 resettlement land plots to arrange for people. By the end of 2020, the entire technical infrastructure system of this resettlement area will be completed.
Regarding schools, it is not until early 2021 that the authorities can start construction. In order to meet the learning needs of children, families having to relocate and relocate, the authorities will arrange for the children to temporarily study at other schools in the area until the school is completed in the redevelopment area. settled.
Regarding the disbursement progress, Dong Nai province has now approved the compensation unit price of Long Thanh International Airport project. In which, the compensation price for rural residential land ranges from 1,392,000 VND to 6,573,000 VND / m2.
Mr. Nguyen Quoc Hung, Vice Chairman of Dong Nai Provincial People's Committee, said that the largest area in the total of 1,810ha of land clearance priority for phase 1 is nearly 1,200 hectares belonging to one member limited liability company. Dong Nai. Currently, Dong Nai People's Committee has issued a decision to recover the entire area and approve and pay compensation for the business.
"We commit to hand over 1,810ha to the investor right in 2020", Mr. Nguyen Quoc Hung affirmed.